Washington Street Rehabilitation to Begin

The paving of Washington St is on schedule to begin construction on October 18th. A pre-construction meeting will be held on October 6th. The grinding and utility work will take place October 18th-October 22nd and the paving work will take place on October 25th- October 29th. 

The remaining work including the crosswalks and striping will be complete by November 19th.  Have questions or concerns about what this project will look like? Watch this Webinar from the Town that will explain the process for our busy main thoroughfare in Yountville.